ever, a modification of this arrangement was made soon after because it became necessary to make certain structural plans of the superstructure in order to get a building permit and in doing this work it proved necessary to revise the caisson foundation designs which had been made previously.
“Only so much additional work was done as was necessary to serve the two purposes cited.
“As stated above, a contract was let to Avery Brundage on December 17, 1920, for nine caisson foundations under the central portion of the building with the intention of proceeding immediately with this portion of the work.
“An informal application was made to the Village of Wilmette for a permit on December 21, 1920. No action was taken but on the contrary some opposition developed and it was necesary to file a formal application for permit, which was done on January 7, 1921. Permit was refused at this time because plans of the building structure were not submitted as required by ordinance. This situation made it necessary to proceed with preparation of general structural plans sufficient to comply with the ordinances of the Village.
“These plans were drawn as rapidly as possible and were filed with a formal application on March 4, 1921, and the building permit was issued on the 19th day of March. This permit covered not only the work then under contract but the construction of the entire building. Under the ordinances of the Village this permit would probably be considered as still in effect, although the Village authorities could require the taking out of a new permit on account of the long suspension of operations.
“Two contracts of considerable amount have been carried out from my plans and under my supervision, namely, with Avery Brundage for nine caissons, amounting to $76,350.00, and with McCarty Brothers for the general basement section, amounting to $108,500.00. In addition to these, there have been several miscellaneous items which are shown on your records and which, with the above aggregate a total of $187,876.35. Payments made to me amount to $8,000.00, which includes payments to apply on account of the extra work of preparing plans for permit and for caissons.
“The Brundage contract for caissons was completed early in the summer of 1921, having been quite sericusly delayed because of the large amount of water encountered in digging the wells for these foundations. These wells were approximately 120 ft. deep and extended about 90 ft below the level of the water in the lake and the drainage canal near by.
Soon after the completion of the caisson contract, plans were submitted to contractors for the basement structure. This covered the foundations other than nine caissons which were required for the outer portions of the building and the complete enclosure of the basement structure up to and including the first floor. It did not include the basement floor, the subdivision of basement space, the finishing of basement nor the installation of any of the mechanical appliances.
“A contract was made with McCarty Brothers of Chicago for this work on August 24, 1921. The starting of the work was somewhat delayed by the time required to get the necessary signatures to the contract. Also the work occupied considerable more time than was anticipated but was finally completed in the fall of 1922.
“Since the completion of the basement contract, no work of importance has been done on
the structure. As it now
stands, the structure comprises
the entire basement enclosure,